“Mare Island Building 655 Demolition & Abatement Project”, from the report for the Public Works Department - Planning Division, published in the “City Manager’s Bi-Weekly Report”, Volume 2, Issue 4, December 6, 2013, from Daniel E. Keen, City Manager, City of Vallejo:
Clean up has been progressing for the Mare Island Building 655 Demolition and Abatement Project. Approximately 70 percent of the south side of the building has been cleared, debris hauled off and materials recycled. Once visually cleared of asbestos material, the south side columns and the wall will be demolished. The north side has yet to be tackled by the contractor.
No comments:
Post a Comment